PGESCo scope included design review, site supervision and project management of Zwitina Combined Cycle 250 MW add-on Project. The scope also included plant material inspection and performance testing for all plant equipment. The scope is to convert the existing 2 X 250 MW Gas Turbine Power Plant into a 2X2X1 Combined Cycle Power Plant for a total capacity of 750 MW.
Project Details | |
Client | PGESCo teamed with Arabian Consultancy Engineering Services “ACESCo” in Libya |
Date of Award | On Hold due to Libyan Circumstances |