Plant Description
Sidi Krir 1&2 station consists of:
- Two indoor condensing steam turbine generator (STG) units, each capable of delivering 320 MW net power at the generator terminals.
- Two outdoor, dual firing, pressurized furnace steam generators.
- Auxiliary equipment including onsite oil storage, a natural gas pressure reducing and handling facility, a desalination plant for plant make-up water, an off-shore cooling water intake structure, a water and waste water treatment facility, a GIS 220 kV indoor switchyard, 220 kV transmission lines, and a housing colony.
Procurement activities for the project included the full scope of contract/purchase order formation and administration activities covering pre-qualification and evaluation of bidders, issuance of bid documents, bid evaluation, contract negotiations, contract award and expedition.
The project contracting plan used a multi-package system. Thirteen (13) contracting packages and seven (7) purchase orders were awarded to different contractors and suppliers to provide the station goods and services. The plant Owner awarded the different packages while PGESCo acted as the Owner authorized representative. The plant was turned over to the Owner and is in stable commercial operation since 2000.
Project Details | |
Owner | West Delta Electricity Production Company |
Location | Alexandria, Egypt |
Date of Award | May 1994 |
Contractual Duration | September 2000 |
Scope | Engineering, Procurement, Project and Construction Management Services |