Nubaria power project includes water/waste water treatment systems to serve the plant water demand of high purity demineralized water required for boiler feed as well as various power plant users. River water from Nubaria canal is supplied via intake structure to feed the water treatment system through power plant pump house where supply pumps and raw water screens is located. The desalination and water/waste water treatment installed in Nubaria power project includes:
Intake Design |
Open intake |
|
Chlorination System |
Hypochlorite Solution injection system |
|
Raw Water Pretreatment System |
Clarification / Multi Media Filtration |
3 x 2016 m3/day |
Demineralization System |
Cation / degasifier /anion / mixed bed deionizer |
3 x 1500 m3/day |
Waste water treatment system |
Oil separation / clarification / filtration / pH adjustment |
2 x 1440 m3/day |
Potable water treatment |
Activated carbon filters and disinfection with sodium hypochlorite dosing |
400 m3/day |
Sewage treatment plant |
Extended Diffused Aeration system |
2 × 200 m3/day |