Kureimat power project includes water/waste water treatment systems to serve the plant water demand of high purity demineralized water required for boiler feed as well as various power plant users. Raw water from Nile River is supplied via intake structure to feed the water treatment system through power plant pump house where supply pumps and raw water screens is located. The desalination and water/waste water treatment installed in El Kureimat power project includes:
Intake Design | Open intake | |
Chlorination System | Hypochlorite Solution injection system | |
Raw Water Pretreatment System | Clarification / Multi Media Filtration | 3 x 2400 m3/day |
Demineralization System | Cation / degasifier /anion / mixed bed deionizer | 3 x 1500 m3/day |
Waste water treatment system | Oil separation / clarification / filtration / pH adjustment | WW 2 x 1440 m3/day
Oil Sep 100 m3/h |
Potable water treatment | Activated carbon filtration+ chlorination | 20 m3/h |
Project Details | |
Owner | Upper Egypt Electricity Production Company |
Location | Upper Egypt |
Date of Award | February 2006 |
Contractual Duration | 18 Months |
Scope | Engineering, Procurement, and Construction Management Services |