Cairo North Water Treatment Facilities

Region:

Status:

 

Cairo North power project includes water/waste water treatment systems to serve the plant water demand of high purity demineralized water required for boiler feed as well as various power plant users. River water from Nile River is supplied via intake structure to feed the water treatment system through power plant pump house where supply pumps and raw water screens is located. The water/waste water treatment installed in Cairo North power project includes:

Intake Design Open intake
Chlorination System Hypochlorite Solution injection system
Raw Water Pretreatment System Clarification / Multi Media Filtration /Sludge Dewatering 2 x 1680 m3/day
Demineralization System Cation / degasifier /anion / mixed bed deionizer 2 x 1680 m3/day
Waste water treatment system API Oil separation / DAF oil separation 2400 m3/day
Project Details
Owner Cairo Electricity Production Company
Location Cairo, Egypt
Date of Award December 2002
Contractual Duration 18 Months
Scope Engineering, Procurement, and Construction Management Services