Abu Qir power project includes desalination and water/waste water treatment systems to serve the plant water demand of high purity demineralized water required for boiler feed as well as various power plant users. Sea water from Mediterranean sea is supplied via intake structure to feed the desalination system through power plant pump house where supply pumps and sea water screens is located. The desalination and water/waste water treatment installed in Abu Qir power project includes :
Intake Design |
Open intake |
|
Chlorination System |
On-site Hypochlorite generation system |
2 x 500 kg cl2/h |
Desalination System |
Multi Effect Distillation with Thermal Vapor compression (MED-TVC) |
10,000 m3/day |
Demineralization System |
Mixed bed deionizer |
2 x 3000 m3/day |
Condensate polisher System |
Externally Regenerated Mixed Beds |
2 x 880 m3/h |
Waste water treatment system |
Oil separation / clarification / filtration / pH adjustment |
240 m3/day |
Sewage treatment plant |
Extended Aeration |
200 m3/day |