Substations in Libya

14 X 220 KV SUBSTATIONS
On-going
PGESCo scope included design review, site supervision and project management of fourteen (14) 220 kV substations. The scope also included material inspection. The project consists of seven 220 kV substations throughout Libya.

3 X 220/400 KV SUBSTATIONS – SABHA, TUBROK AND MELITA
On-going
PGESCo scope included design review, site supervision and project management of three (3) 220/400 kV substations. The scope also included material inspection

7 X 400 KV SUBSTATIONS
Completed 2008
PGESCo scope included design review, site supervision and project management of the project. The scope also included plant equipment material inspection and performance testing as well as training and technology transfer to GPCOEWG (General People’s Committee of Electricity, Water and Gas). The project consists of seven (7) 400/220 kV substations throughout Libya.