Plant Description
Talkha power project consists of two 250 MW combustion turbine generators (CTGs). Each one feeds exhaust gases to its respective unfired heat recovery steam generator (HRSG). Steam from the two HRSGs feeds one 250 MW, reheat, condensing steam turbine generator (STG).
The estimated 750 MW net output is achieved by burning natural gas in the CTGs with no supplementary firing in the HRSGs. Nitrogen oxide (NOx) emissions are controlled by dry low-NOx (DLN) combustors. An inlet air filtration system is included to supply suitably filtered combustion air to the CTGs. The steam exhausted from the steam turbine feeds a once-through cooling, single-pass, divided water box condenser.
Power is generated at 21 kV (or manufacturer standard voltage) in the CTGs and the STG, stepped up through main transformers, and fed to the utility grid via the existing 220 kV (GIS) switchyard. The Damietta branch of the Nile River provides the plant cooling water.
The project contracting plan utilized a multi-package system. Eight (8) contracting packages and purchase orders procured the equipment and services.
Project Details | |
Owner | Middle Delta Electricity Production Company |
Location | Middle Delta, Egypt |
Date of Award | October 2003 |
Contractual Duration | 49 months |
Scope |
- All conceptual and detailed design of plant systems - Preparation of all tenders, the documents included commercial and legal terms and followed the financing institutes and Owner procurement guidelines - Project management, construction management, startup and commissioning management, which included initial operation support. |