Baiji Power Plant 1014 MW (6XSGT5-PAC 2000E, Dual Fuel + Heavy Fuel Oil

Region:

Status:

Baiji power project is a 1014 MW gas fired simple cycle power generation project of appx 1014 MW at BAIJI, Iraq. The Contractor was engaged to provide engineering, procurement and construction services to the Owner. These included the design, manufacture, delivery, erection and installation of equipment including gas turbine-generator sets supplied by SIEMENS, engineering and design for balance of plant (BOP) items, tie-in to existing infrastructure, painting, setting to work, BOP commissioning and testing, and providing training programs for plant personnel in equipment design, operation and maintenance within the scope of the Contractor scope on a lump sum price basis.Baiji-Power-Plant-Project-In-Iraq-2

Project Details
Owner Ministry of Electricity of IRAQ, General Directorate for Gas Power Plants Projects, a corporation incorporated under the laws of the Republic of Iraq
Client Orascom Construction
Location Baiji, Salahaldeen, Iraq
Date of Award July 2012
Contractual Duration 21 months
Scope Responsible for performing the engineering scope of works including developing detailed engineering works, preparing technical specifications, preparing project material requisitions, preparing technical portions of tender documents, evaluating technical bids, supporting EPC Contractor during the pre-award phase to select the appropriate bidders and pre-award negotiations, reviewing subcontractors technical submittals, preparing detailed project time schedules, supporting the EPC Contractor in preparing works breakdown for billing purposes to the Owner and following up the Owner approval of engineering documents.