Banha Water Treatment Facilities

Region:

Status:

Banha power project includes water/waste water treatment systems to serve the plant water demand of high purity demineralized water required for boiler feed as well as various power plant users. Raw water Nile River is supplied via intake structure to feed the water treatment system through power plant pump house where supply pumps and raw water screens is located. The water/waste water treatment installed in Banha power project includes:

Intake Design Open intake
Chlorination System Hypochlorite Solution injection system
Raw Water Pretreatment System Clarification + Ultra filtration (UF) 2280 m3/day
Demineralization System Cation / degasifier /anion / mixed bed deionizer 3 x 1800 m3/day
Waste water treatment system Oil separation / clarification / filtration / pH adjustment 2400 m3/day
Potable water treatment UF + Activated carbon filtration + chlorination 100 m3/day
Sewage treatment plant Packaged Type – Extended aeration 100 m3/day
Project Details
Owner Middle Delta Electricity Production company
Location Middle Delta, Egypt
Date of Award July 2012
Contractual Duration 19 Months
Scope Engineering, Procurement, and Construction Management Services