Giza North power project includes water/waste water treatment systems to serve the plant water demand of high purity demineralized water required for boiler feed as well as various power plant users. Raw water Nile River is supplied via intake structure to feed the water treatment system through power plant pump house where supply pumps and raw water screens is located. The water/waste water treatment installed in Giza North power project includes:
Intake Design |
Open intake |
|
Chlorination System |
Chlorine Gas feed system |
3 x 1200 kg Cl2/h |
Raw Water Pretreatment System |
Clarification + Ultra filtration (UF) |
3 x 2520 m3/day |
Demineralization System |
Cation / degasifier /anion / mixed bed deionizer |
3 x 2040 m3/day |
Waste water treatment system |
Oil separation / clarification / filtration / pH adjustment |
5280 m3/day |
Potable water treatment |
UF + activated carbon filtration+ chlorination |
80 m3/day |
Sewage treatment plant |
Extended aeration |
80 m3/day |