Plant Description
Suez power projects is designed to include a 1 x 650 MW steam thermal power plant to interconnect with the National Unified Power System (NUPS) through a 220 KV GIS switchyard. The power block is comprised of one Rankine cycle turbine generator unit with a nominal rated capacity of 650 MW. The unit is capable of generating rated capacity using natural gas, residual (mazout) oil, or a combination of both. The unit station arrangement includes an enclosed turbine building, an open boiler building, a control room, and all associated structures and facilities.
The project contracting plan utilized a multi-package system. Nineteen (19) contracting packages and purchase orders procured the equipment and services.
Project Details | |
Owner | East Delta Electricity Production Company |
Location | Suez, Egypt |
Date of Award | July 2010 |
Contractual Duration | 57 months |
Scope |
- All conceptual and detailed design of plant systems - Preparation of all tenders, the documents included commercial and legal terms and followed the financing institutes and Owner procurement guidelines - Project management, construction management, startup and commissioning management, which included initial operation support. |